STUDI KOORDINASI SISTEM PENGAMAN PADA TRANSFORMATOR DAYA PT. PLN (PERSERO) P3B SUB REGION BALI DI GARDU INDUK PADANG SAMBIAN
Main Article Content
Abstract
The transformer is the main equipment that is very important at the substation. However, sometimes there can be damage to the transformer used. Damage to the transformer will be able to disrupt the distribution of electricity, so it must get the right security, determining the right relay setting is an attempt to protect equipment, system security and consumer needs from possible disruption in the distribution system.
In some roles, efforts to protect the power transformer if there is a short circuit between phase and phase to the ground, then this study will study the coordination of the security system of power transformers in Padang Sambian main substation.
The results of the calculation of overcurrent relay (OCR) on the 150KV transformer that has been done is obtained the results of the CT primary side current setting of 254.1 A and for the secondary side of 3.178 A. For the actual working time of the relay is 0.91 seconds, if the current exceeds value of this setting there will be a trip. The results of the calculation of overcurrent relay (OCR) on the 20KV transformer that has been done is obtained the results of the CT primary side current setting of 1905 A and for the secondary side is obtained for 4.76 A. For the actual working time relay result is 3.69 seconds, if the current exceeds the value of this setting there will be a trip.
Downloads
Article Details
This work is licensed under a Creative Commons Attribution 4.0 International License.