Studi Analisa Koordinasi Relai GFR Incoming Busbar 20 KV dan GFR Saluran untuk Mengamankan Gangguan Satu Phasa ke tanah di Transformator 3 Gardu Induk Kapal

  • I Gede Krisnayoga Kusuma Universitas Udayana
  • I Gede Dyana Arjana Universitas Udayana
  • I Wayan Arta Wijaya Universitas Udayana

Abstract

Disruption of the distribution system is generally caused by a short circuit that causes overcurrent, one single phase short circuit to ground. Single phase to ground disturbances that occurred at the feeder should be secured by a ground fault relays in feeders. However, due to an error of coordination, interference with the feeder perceived also to the incoming side of the transformer so that ground fault relays on the incoming 20 kV ordered PMT 20 kV at the transformer side open. Working time ground fault relays in feeders Peguyangan is for 0.25 seconds. While working time ground fault relays in the incoming 20 kV is for 0.5 seconds. This indicates that differences in work time relay by 0.25 seconds is considered selective. The event of disruption of the ground phase, GFR relay coordination in securing the area of ??interference must be gradual. Where the value of working time ground fault relays in the base should be longer than the time ground fault relays working on a feeder. It aims to work ground fault relays working order, so that errors can be avoided in the security and do not lead to the spread of disturbed areas.

Downloads

Download data is not yet available.

Author Biography

I Gede Krisnayoga Kusuma, Universitas Udayana
turnitin check 10%, 9 oktober 2016

References

I. G. M. W. M. Sidemen, R. S. Hartati, and Linawati, “Peramalan Beban Listrik Harian dengan Metode Adaptive Neuro Fuzzy Inferrence System,” Teknik Elektro, Vol. 13, No. 1 Januari – Juni 2014

I. Baskara, I. W. Sukerayasa and W. G. Ariastina, “Studi Koordinasi Peralatan Proteksi OCR dan GFR pada Penyulang Tibubeneng,” Teknik Elektro, Vol. 14, No. 2, Juli – Desember 2015

PT. PLN UDIKLAT, Proteksi Gardu Induk, PT. PLN (Persero) P3B, Semarang, Indonesia : 2013.

PT. PLN, Modul Pelatihan Relai OCR, PT. PLN (Persero) P3B, Jakarta, Indonesia : 2005.

Komari, S. Soekarto, and Wirawan, Kaidah Umum Penyetelan Rele, PT. PLN (Persero), Semarang, Indonesia : 1995.
Published
2017-08-31
How to Cite
KRISNAYOGA KUSUMA, I Gede; DYANA ARJANA, I Gede; ARTA WIJAYA, I Wayan. Studi Analisa Koordinasi Relai GFR Incoming Busbar 20 KV dan GFR Saluran untuk Mengamankan Gangguan Satu Phasa ke tanah di Transformator 3 Gardu Induk Kapal. Majalah Ilmiah Teknologi Elektro, [S.l.], v. 16, n. 2, p. 20-24, aug. 2017. ISSN 2503-2372. Available at: <https://ojs.unud.ac.id/index.php/mite/article/view/ID23861>. Date accessed: 19 nov. 2024. doi: https://doi.org/10.24843/MITE.2017.v16i02p04.

Keywords

System Protection , OCR and GFR , Ground fault