Analisisi Energi Listrik Terselamatkan pada Penyulang Bangli PT. PLN (Persero) Area Bali Timur dengan Beroperasinya PLTS Kayubihi

  • valentinus gerald gambut Universitas udayana
  • Rukmi Sari Hartati Teknik Elektro Unud
  • Antonius Ibi Weking Teknik Elektro Unud

Abstract

Abstract— Bangli Feeder has 3 Feeder, namely Kota Feeder, Kayubihi Feeder and Tembuku Feeder. This Feeder has a main power supply is obtained from the Gianyar Main Relay Station. Currently Kayubihi Solar Cell Power Plant directly interconnected to the Feeder Bangli. With Solar cell power plant connected on Kayubihi Feeder, it will result in a change in the performance of feeder Bangli. This involves changes in the
performance of of the electrical energy that is channeled along the Bangli feeder system reliability. The addition of the feeder solar cell power plant create electrical energy saved Bangli feeder decline. Bangli feeder without generating large solar power energy not supplied amounted to 10.426 kWh. Energy not
supplied Bangli Feeder after obtaining additional supplies of solar power generating is 1.505 kWh.

Downloads

Download data is not yet available.
Published
2016-06-25
How to Cite
GAMBUT, valentinus gerald; HARTATI, Rukmi Sari; WEKING, Antonius Ibi. Analisisi Energi Listrik Terselamatkan pada Penyulang Bangli PT. PLN (Persero) Area Bali Timur dengan Beroperasinya PLTS Kayubihi. Majalah Ilmiah Teknologi Elektro, [S.l.], v. 15, n. 1, p. 69-74, june 2016. ISSN 2503-2372. Available at: <https://ojs.unud.ac.id/index.php/mite/article/view/18252>. Date accessed: 19 nov. 2024. doi: https://doi.org/10.24843/MITE.2016.v15i01p12.

Keywords

PLTS; ENS (Energy Not Supplied);AENS (Average Energy Not Supplied).