Analisa Indeks Keandalan pada Pembangkit Listrik Tenaga Mesin Gas (PLTMG) MPP Flores

  • Joannes Mario Graciano Kapu Universitas Udayana
  • Lie Jasa
  • Rukmi Sari Hartati

Abstract

Electrical energy is a vital need that is increasing from year to year. As a need, the provision of electricity needed by consumers needs to be considered so that electrical energy can be distributed reliably, safely and environmentally friendly and in accordance with established standards. To measure the ability of the generator to meet electricity needs, a reliability index is needed. This study aims to assess the reliability index at the Flores MPP Gas Engine Power Plant (PLTMG). The LOLP (Loss Of Load Probability) index value is used to perform calculations. In this study, in finding the reliability index of a generation system, referring to SPLN: 68-1A: 1986, that is for the Java-Bali system it is 3 days/year and for systems outside Java-Bali it is 3.5-5 days/year. Based on the research results, the LOLP value of the Flores MPP PLTMG in 2022 is 4.5295 days/year and based on SPLN: 68-1A: 1986, therefore the Loss Of Load Probability (LOLP) value at the Flores MPP PLTMG is said to be reliable because it meets the standards.

Downloads

Download data is not yet available.

References

[1] Sulasno, I. (2001). Teknik dan Sistem Distribusi Tenaga Listrik. Badan Penerbit Universitas Diponegoro, Semarang
[2] Cekum, A. (2019). Studi Keandalan Pembangkit Listrik Tenaga Diesel (PLTD) Sukaharja Kabupaten Ketapang. Journal of Electrical Engineering, Energy, and Information Technology (J3EIT), 7(2).
[3] SPLN : 68-1A : 1986
[4] Laporan Pelaksanaan Monitoring Lingkungan Pembangkit Listrik Tenaga Mesin Gas (PLTMG) MPP Flores
[5] Syahputra, R., Noor, F., & Mujaahid, F. (2020). Analisis Indeks Keandalan Pembangkit Listrik Tenaga Hibrid Angin-Surya Menggunakan Metode EENS. Semesta Teknika, 23(1), 92-105.
[6] Asharf, S., Fauxan., & Nazaruddin, N. (2020). Studi Pengaruh Perubahan Temperatur Terhadap Kinerja Engine pada PLTMG Panaran PT. Bright Batam. Jurnal TEKTRO, 4(2)
[7] GAFUR, A. (2016). Studi Kelayakan Teknis dan Ekonomis Rantai Pasok Gas Alam ke Pembangkit Listrik di Kepulauan Kangean.
[8] RUPTL 2015-2024, PT. PLN Persero
[9] Marsudi, djiteng. 2005. Pembangkitan Energi Listrik. Erlangga. Jakarta
[10] Kurniadi, D. (2019). Analisis Prakiraan Permintaan Dan Penyediaan Energi Listrik Tahun 2018-2025 Di Pt. Pln (Persero) Area Rengat Riau (Doctoral Dissertation, Universitas Islam Negeri Sultan Syarif Kasim Riau).
[11] Hartati, R. (2007). PENENTUAN ANGKA KELUAR PERALATAN UNTUK EVALUASI KEANDALAN SISTEM DISTRIBUSI TENAGA LISTRIK. Majalah Ilmiah Teknologi Elektro, 6(2)
[12] Manuaba, I., & Sukerayasa, I. (2004). STUDI KEANDALAN PENYULANG 20 kV DI GARDU INDUK PADANG SAMBIAN MENGGUNAKAN METODE SIMULASI MONTE CARLO. Majalah Ilmiah Teknologi Elektro, 3(2)
[13] Gunawan, A.H., & Ferdinan, F. (2002). Kajian Kehandalan SDH Pada JARLOKAF. Elektronika Indonesia, (44)
[14] Parsa, I. Made, Zeth By Tanu, and Silvester Charlianus Hadi. "EVALUASI JARINGAN DISTRIBUSI TERHADAP KETERSEDIAAN DAYA LISTRIK PADA FKIP UNIVERSITAS NUSA CENDANA KUPANG." Jurnal Teknologi 13, no. 1 (2019): 30-38.
[15] Subekti, Massus, Uno Bintang Sudibyo, and I. Made Ardit. "Analisis Keandalan Sistem Perencanaan Pembangkit Listrik PLN Region 3 Tahun 2008-2017." In Prosiding Seminar Nasional Teknoin. 2008.
[16] SYAHRIAL, S., SAWITRI, K., & GEMAHAPSARI, P. (2017). Studi Keandalan Ketersediaan Daya Pembangkit Listrik pada Jaringan Daerah “X”. ELKOMIKA: Jurnal Teknik Energi Elektrik, Teknik Telekomunikasi, & Teknik Elektronika, 5(1), 93.
[17] Ilmi, F. N. (2022). ANALISIS KEANDALAN OPERASI SISTEM PEMBANGKITAN SULAWESI BAGIAN SELATAN BERDASARKAN INDEKS PROBABILITAS KEHILANGAN BEBAN= RELIABILITY ANALYSIS OF THE SOUTH SULAWESI POWER PLANT SYSTEM OPERATION BASED ON LOSS OF LOAD PROBABILITY INDEX (Doctoral dissertation, Universitas
[18] Hasanuddin).
[19] Marsudi, djiteng, 2006. Operasi Sistem Tenaga Listrik. Graha Ilmu. Yogyakarta.
[20] Muchafadhoh, 2018. Studi Analisa Indeks Keandalan pada Pembangkit Listrik Tenaga Uap (PLTU) PT. PJB UP Gresik Menggunakan Perhitungan LOLP (Loss Of Load Probability). Universitas Muhamaddiyah Yogyakarta.
[21] W.D. Marsh, 1980. Economics of Electric Utility Power Generation, Clarendon Press - Oxford, University Press, N.Y.
Published
2024-08-31
How to Cite
KAPU, Joannes Mario Graciano; JASA, Lie; HARTATI, Rukmi Sari. Analisa Indeks Keandalan pada Pembangkit Listrik Tenaga Mesin Gas (PLTMG) MPP Flores. Majalah Ilmiah Teknologi Elektro, [S.l.], v. 23, n. 1, p. 125-130, aug. 2024. ISSN 2503-2372. Available at: <https://ojs.unud.ac.id/index.php/mite/article/view/115215>. Date accessed: 15 oct. 2024. doi: https://doi.org/10.24843/MITE.2024.v23i01.P13.