KORELASI ANTARA PENGENDALIAN KUALITAS RENCANA PELAKSANAAN DENGAN KINERJA PROYEK KONSTRUKSI (Studi Kasus Pada Satuan Kerja Non Vertikal Tertentu Pengembangan Kinerja Pengelolaan Air Minum Provinsi Nusa Tenggara Timur)
Abstract
In the construction project activity, planning is used as a reference by theimplementation unit and become a standard of the project implementation, and
includes: technical specifications, schedule and budgeting. Inaccurate planning,
imperfect investigation of the project location, lack of experience and ability in
managing the project and lack of professionalism of the service provider are
closely linked to the result of the process of a construction project (project
performance). This research is conducted within the physical activity
scope/construction stage that aims to find out the relation between influence quality
control of the implementation plan and the performance of the construction project
(cost and time performances). Primary data is obtained from questionnaries and is analyzed using SPSS. The
research found that the regression model chosen is nonlinear regression model
where the equation Y1=1,122+0.282X1+0,208X3+0,292X15+0,325X19+0,318X9 and
Y2=1,187+0.395X2+0,310X5+0,263X16+0,196X6+0,247X11 is for cost factor and
time factor respectively. The coefficients found in each regression model have
positive value. This shows that there is positive correlation between quality control
of the implementation plan and the construction project performance.
Factors affecting the cost performances are quality of planning resources for
drawing design, quality of bidding of the service provider, quality control of
service provider resources, the design revision, the project controlling while for the
time performances there are quality of design drawing, quality of technical bidding
contractors, quality of the project controlling, quality of service provider resources,
and project implementation planning.
Downloads
Download data is not yet available.
How to Cite
YANSEN, Wayan.
KORELASI ANTARA PENGENDALIAN KUALITAS RENCANA PELAKSANAAN DENGAN KINERJA PROYEK KONSTRUKSI (Studi Kasus Pada Satuan Kerja Non Vertikal Tertentu Pengembangan Kinerja Pengelolaan Air Minum Provinsi Nusa Tenggara Timur).
Jurnal Ilmiah Teknik Sipil, [S.l.], nov. 2012.
ISSN 2541-5484.
Available at: <https://ojs.unud.ac.id/index.php/jits/article/view/3642>. Date accessed: 22 nov. 2024.
Issue
Section
Articles
Keywords
Nonlinear regression model, Cost performance, Time performance.