AKSELERASI PENYELESAIAN PROYEK DENGAN ANALISA PERTUKARAN WAKTU DAN BIAYA ( TIME COST TRADE OFF )

  • Dewa Ketut Sudarsana

Abstract

Three main objective in the constructing construction project there
are cost, time and quality. Cost and time have great relationship and depending once
than the other. Some time in the field we founded nonconform between the duration of
completion in the contract with the realization. On the case studi of Pembangunan
Stadion Olah Raga Buruan in Kecamatan Blahbatuh, Gianyar, the owner need that
project be completed earlier than the agreement completion. The influence of
acceleration completion project with the project cost need to study.
In this case the CPM (Critical Path Method) be used with compressed the duration of
activities on the critical path and do time cost trade off analysis. The project cost
means is the total cost project. The total project cost are direct cost (material, workers
and equipment) and indirect cost (the other direct cost).
The outcome of analysis be founded that accelerate (crash) maximum 65 days done, so
the earliest completion by 265 days without total project cost added. The project
completion optimum be founded too, with project duration 316 days and project total
cost minimum amount Rp. 13.358.425.131,28, that’s below 0.55 % than project cost in contract. This phenomenon show that accelerate the duration completion project not
always be increasing the total project cost, because the duration of completion project
in the contract probably does not the optimum duration of completion.

Downloads

Download data is not yet available.
How to Cite
SUDARSANA, Dewa Ketut. AKSELERASI PENYELESAIAN PROYEK DENGAN ANALISA PERTUKARAN WAKTU DAN BIAYA ( TIME COST TRADE OFF ). Jurnal Ilmiah Teknik Sipil, [S.l.], nov. 2012. ISSN 2541-5484. Available at: <https://ojs.unud.ac.id/index.php/jits/article/view/3396>. Date accessed: 22 nov. 2024.
Section
Articles

Keywords

accelerate duration, project cost, time cost trade off