Redesain Dan Analisa Kelayakan PLTMH 25 KW Desa Susuan Karangasem Bali
Abstract
Abstract—The need for electricity in Indonesia has always increased from year to year. In Indonesia, the use of fossil power plants is still widely used. Water energy itself is an alternative to replace fossil fuels in general, one of which is a Micro Hydro Power Plant. This research was made to identify MHP in Sususan Karangasem Village can be revitalized (rebuilt) through the measurement and calculation of the potential of water resources with the flow duration curve method with a probability exceeding 80%. To analyze the feasibility of PLTMH financial analysis is carry out namely Net Present Value (NPV), Internal Rate Ratio (IRR), Payback Period (PP) and Benefit Cost Ratio (BCR). The results of the analysis found that the potential of the current Karangasem MHP is 25.18 kWh with annual electricity generation of 220.577 kWh / year and electricity BPP = Rp. 774. per kWh. From the results of the analysis, the MHP of Susuan Karangasem Village can be sayto be feasible for revitalization.
Keywords: Micro Hydro Power Plant (MHP), Hydrological Analysis, Energy Economy Analysis, Revitalization.
Downloads
References
[2] S. Kumara, Nyoman. “Telaah Terhadap Program Percepatan Pembangunan Listrik Melalui Pembangunan PLTU Batubara 10.000 MW”. Majalah Ilmiah Teknologi Elektro. ISSN 2503-2372. Universitas Udayana, Agustus 2012.
[3] N. S. Kumara, W. G. Ariastina, I. W. Sukerayasa and I. A. D. Giriantari, "On the potential and progress of renewable electricity generation in Bali". 2014 6th International Conference on Information Technology and Electrical Engineering (ICITEE), Yogyakarta, 2014, pp. 1-6. doi: 10.1109/ICITEED.2014.7007944
[4] PT. PLN (Persero). Sustainability Report PLN 2015. Indonesia, 2015.
[5] Disbud Karangasem. http://disbud.karangasemkab.go.id/blog/data-budaya/desa-pakraman-susuan/. [Online]
[6] G. Yasa, “Analisis Pengelolaan Pembangkit ListrikTenaga Mikrohidro di Desa Susuan Karangasem Secara Tekno Ekonomis”. Tesis, Manajemen Energi, Teknik, Universitas Udayana, 2011.
[7] Indarto, Juwono dan Rispiningtati. “Kajian Potensi Sungai Srinjing untuk Pembangkit Listrik Tenaga Mikrohidro (PLTMH) Brumbung di Kabupaten Kediri”. Jurnal Teknik Pengairan, 2012, Vol. 3 No. 2 Desember: 174-184.
[8] Ismail dan Supriono. “Analisis Ekonomi Energi Perencanaan Pembangkit Listrik Tenaga Mikrohidro Merangun (Desa Merangun, Kec. Nanga Taman, Kab. Sekadau)”. Jurnal ELKAHA, Vol. 5, No. 1 Maret 2013.
[9] Tambunan dan Setiabudy. “Analisis Kelayakan Pembangunan Pembangkit Listrik Tenaga Mikrohidro (PLTMH) di Desa Nyomplong Bogor”. Fakultas Teknik, Universitas Indonesia. 2014.
[10] Sudargana, Karnoto, Hari Nugroho, “Studi Kelayakan dan Perancangan Pembangkit Listrik Tenaga Mikrohidro di Dukuh Pekuluran Kec. Doro Kab. Pekalongan”, Jurnal Rotasi, Vol 3, No2, April 2005.
[11] Eiji, Ohno. “Cost-benefit Analysis of Small Hydroelectric Generation Project utilizing Resident Volunteers”. Faculty of Urban Science, Meijo University. Japan. 2016.
[12] Pemanfaatan Sumber Energi Terbarukan untuk Penyediaan Tenaga Listrik. PERMEN ESDM. No. 12 Tahun 2017
[13] Besaran Biaya Pokok Penyediaan Pembangkitan PT. Perusahaan Listrik Negara (Persero) Tahun 2017. KEPMENESDM No. 1772 K/20/MEM/2018.
[14] Suparyawan, DPD; Kumara, INS; Ariastina, Wayan G. “Studi Perencanaan Pembangkit Listrik Mikrohidro Di Desa Sambangan Kabupaten Buleleng Bali”. Majalah Ilmiah Teknologi Elektro, [S.l.], v. 12, n. 2. ISSN 2503-2372. Bali. 2013
[15] Kumara, D. P. D. Suparyawan, W. G. Ariastina, W. Sukerayasa and I. A. D. Giriantari, "Microhydro powerplant for rural area in Bali to generate green and sustainable electricity". International Conference on Smart Green Technology in Electrical and Information Systems (ICSGTEIS), pp. 113-117, doi: 10.1109/ICGTEIS.2014.7038741. Kuta, 2014.
[16] Purnama, Ady. Studi Kelayakan Pembangunan Pembangkit listrik Tenaga Mikro Hidro Studi Kasus PLTMH Minggir pada Saluran Irigasi Minggir di Padukuhan Klagaran Desa Sedangrejo Kecamatan Minggir Kabupaten Sleman. Jurnal UNSA. Jilid 10. No. 15 Oktober 2011
This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.
This work is licensed under a Creative Commons Attribution 4.0 International License